Pareto-scheduling with family jobs or ND-agent on a parallel-batch machine to minimize the makespan and maximum cost

4OR(2021)

引用 2|浏览1
暂无评分
摘要
We study Pareto-scheduling on an unbounded parallel-batch machine that can process any number of jobs simultaneously in a batch. The processing time of a batch is equal to the maximum processing time of the jobs in the batch. We consider two Pareto-scheduling problems. In one problem, the jobs are partitioned into families and the jobs from different families cannot be processed together in the same batch. We assume that the number of families is a constant. The objective is to minimize the makespan and the maximum cost. In the other problem, we have two agents A and B , where each agent E∈{A,B} has its job set 𝒥_E , called the E -jobs. Assuming that the job sets 𝒥_A and 𝒥_B are not necessarily disjoint, we call the agents ND agents. The objective is to minimize the makespan of the A -jobs and the maximum cost of the B -jobs. We provide polynomial-time algorithms to solve the two Pareto-scheduling problems.
更多
查看译文
关键词
Pareto-scheduling,parallel-batch machine,family jobs,ND agents,polynomial time
AI 理解论文
溯源树
样例
生成溯源树,研究论文发展脉络
Chat Paper
正在生成论文摘要