The Integrated Problem of Construction Project Scheduling and Multiskilled Staff Assignment with Learning Effect

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT(2023)

引用 0|浏览2
暂无评分
摘要
Effective multiskill resource scheduling requires comprehensive workforce assignments. Drawing on the multiskill project scheduling problem perspective, this study investigates the integrated problem of project scheduling and multiskilled staffing based on a more realistic perspective that human skill level is dynamic and has a variable activity duration caused by the learning effect. An integer linear programming model is innovatively constructed to solve the problem directly. Moreover, an adapted tabu search algorithm with six resource-oriented priority strategies is designed to solve large-scale problems efficiently. Based on a realistic construction project case and numerical instances, comprehensive computational experiments are conducted to validate the proposed algorithm. The findings reveal the impact of different resource strategies on project duration and personal skill growth, particularly through the optimization of project scheduling according to the dynamic scenarios. The research extends conventional project scheduling knowledge and its methods by solving complex scheduling problems for improved project objectives and employee value. In practice, the model and the algorithm can be integrated into the project management information system for strategizing a plan of project scheduling and staff assignment proactively.
更多
查看译文
关键词
Construction project scheduling, Multiskilled staff assignment, Learning effect, Dynamic skill, Tabu search algorithm
AI 理解论文
溯源树
样例
生成溯源树,研究论文发展脉络
Chat Paper
正在生成论文摘要