Tubing Dimension Optimization for the Development of an Offshore Gasfield

FDMP-FLUID DYNAMICS & MATERIALS PROCESSING(2023)

引用 0|浏览4
暂无评分
摘要
L1 is one of the largest offshore gas fields currently under development. In order to optimize the related design, nodal analysis is applied (including proper consideration of the plant productivity, sensitivity to the tubing size, erosion effects, liquid carrying performance, and tubing string). As a result of such approach, it is shown that 13Cr material should be chosen as the appropriate tubing material. Moreover, 3-1/2 inches 9.3 lb/ft N80 tubing, 4-1/2 inches 12.75 lb/ft N80 tubing, 5-1/2 inches 17 lb/ft N80 tubing should be used for a gas production rate under 80 x 104 m3/d, between 80 x 104 m3/d and 120 x 104 m3/d and above 120 x 104 m3/d, respectively.
更多
查看译文
关键词
Offshore gas fi eld, tubing selection, nodal analysis, tubing erosion prediction