Renovation of a Scraper Unit of a Muon Production Target at J-PARC

Proceedings of the 14th International Conference on Muon Spin Rotation, Relaxation and Resonance (μSR2017)(2018)

引用 0|浏览2
暂无评分
摘要
We developed a beam scraper that can handle up to 2 MW proton beams and replaced the conventional scraper with the new one.For the replacement work, Monte Carlo calculation code was carried out to evaluate the protection of induced radiation by 3-GeV proton beam irradiation.New scraper is running smoothly at 0.5 MW operation and can withstand the upgrading of the beam power that is planned in the future.