Study On The Rational Excavation Sequence Of Deep Buried Perpendicular Tunnel In Beijing

CIVIL ENGINEERING IN CHINA - CURRENT PRACTICE AND RESEARCH REPORT(2010)

引用 0|浏览0
暂无评分
摘要
The paper analyzed the different excavation sequences "the upper tunnel first" and "the lower tunnel first" under the same conditions, either surface subsidence shape and curve or moment of the preliminary lining, "the upper tunnel first" excavation sequence was the better by comprehensive comparison, so "the upper tunnel first" was the more reasonable excavation sequence, which could provide technical support to the related project, and provide cross-reference the tunnel excavation experience which has a similar geological conditions as Beijing.
更多
查看译文
关键词
deep buried perpendicular tunnel, excavation sequence, numerical simulation, the upper tunnel first, subsidence curve
AI 理解论文
溯源树
样例
生成溯源树,研究论文发展脉络
Chat Paper
正在生成论文摘要