Commissioning Status of the Linac for the Facility for Rare Isotope Beams
JOURNAL OF THE KOREAN PHYSICAL SOCIETY(2020)
摘要
The Facility for Rare Isotope Beams will be completed in late 2021. We report here on the current efforts to commission the first stages of the 200-MeV/u superconducting, continuous wave heavy-ion linac. The statuses of the cryogenic plant and its distribution system, the accelerator cryomodule commissioning and operations, the ion source and front end transport development, the radio-frequency quadrupole commissioning, and thenbeam dynamics development to support high-power operation are reviewed. Plans for commissioning the remainder of the linac systems are presented.