The Commissioning of the WEST Tokamak: Experience and Lessons Learned

IEEE Transactions on Plasma Science(2020)

引用 8|浏览129
暂无评分
摘要
The integrated commissioning of the tungsten (W) environment in steady-state tokamak (WEST) was started with the superconducting magnet cool-down and completed one year after by the injection of 2.5 MW of additional power. It consisted of several steps: local system commissioning, integrated commissioning without plasma, and first plasma operation. This article reviews these WEST commissioning pha...