Stochastic Project Scheduling with Hierarchical Alternatives

Applied Mathematical Modelling(2018)

引用 33|浏览28
暂无评分
摘要
•We investigate a project scheduling problem with hierarchical alternative methods and uncertain activity durations.•The general mathematical model and the corresponding chance constraint model are formulated.•A metaheuristic combining sampling average approximation with artificial algae algorithm is developed.•Experimental results show that the proposed method outperforms GA.
更多
查看译文
关键词
Project scheduling,Stochastic activity duration,Hierarchical alternative method,Stochastic chance constraint,Sample average approximation (SAA),Discrete artificial algae algorithm (DAAA)