Completed installations and the individual commissioning of the KSTAR MG system

Fusion Engineering and Design(2014)

引用 5|浏览10
暂无评分
摘要
•All components of the MG system were made from each professional supplier and installed completely in the NFRI site.•The building and the overhead crane which need to install the MG system, were built in two sections. One is for the bearing, rotor and stator and the other section is for the VVVF and excitation system.•The dummy coil testing will commence in July 2013 and the comprehensive performance test of MG will be tested from August when the MPS commissioning is processing with superconducting coil.
更多
查看译文
关键词
KSTAR,Power system,Motor generator,Flywheel,Energy storage